ℹ About This Calculator
At concept and feasibility stage you often need an electrical budget before any detailed design exists. This estimator produces an order-of-magnitude bill of quantities and cost from a handful of inputs — built-up area, number of floors, connected load and supply voltage — using typical per-square-metre and per-kW allowances for cabling, distribution boards, lighting, small power and the incoming supply, so you can frame a budget and compare options quickly.
These figures are order-of-magnitude only — real costs depend on specification, local rates, market conditions and the detailed design. The estimator is for early budgeting, option comparison and sanity-checking a quote, not for tendering. Always replace it with a measured BOQ from drawings and current supplier pricing before committing to a number.
Concept BOQ Method
Order-of-magnitude estimate
Step 1 - Apply per-m² allowances for lighting, small power and containment to the built-up area. Step 2 - Add per-kW allowances for the main and sub-main distribution scaled to the connected load. Step 3 - Add lump sums for the incoming supply, main panel and earthing based on load and voltage. Step 4 - Sum the sections into a headline BOQ value and a per-m² rate for benchmarking.
Worked Example
For a 5,000 m² office over 5 floors with a 600 kW connected load, applying typical per-m² allowances for lighting, small power and containment plus per-kW main/sub-main and a supply lump sum yields a headline electrical budget and a per-m² benchmark rate — enough to seed the project cost plan before detailed design begins.
Using a Concept Electrical Estimate
What it is good for
Early budgets, feasibility studies and quick option comparisons — when you need a defensible number before there is anything to measure. It also helps benchmark a contractor rate against a typical per-m² figure.
What it is not
It is not a tender document. Specification, local labour and material rates, market conditions and the detailed layout all change the outcome, so the estimate carries a wide uncertainty band.
Refining the number
As the design develops, replace the allowances with measured quantities from the single-line diagram, cable schedules and layouts priced at current rates. The gap between the concept estimate and the measured BOQ is a useful measure of how the design has settled.
Frequently Asked Questions
Related Calculators
Related Articles
🧮 114 Free MEP Calculators
Browse all HVAC, Electrical, Plumbing, Fire, Gas and Mechanical calculators - IS/IBC/ASHRAE compliant, free PDF export.
Browse All Calculators →⚠️ Disclaimer: For preliminary engineering design only. Verify all results with a licensed engineer before use. Full disclaimer →